Part 1 | Minimum Standards of Construction of Poultry Processing Premises

                      1.2.4   Vehicle loading and unloading areas, vehicle cleaning
                              areas and inedible material collection areas must be
                              paved and drained.

                      1.2.5   Holding areas for live birds shall be sheltered, paved
                              and drained and provided with adequate ventilation and
                              cooling.
                      1.2.6   The buildings should be well ventilated and lit, kept clean
                              and free from vermin, dust and other conditions that
                              would contaminate poultry products.

                      1.2.7   Necessary water, electricity and drainage facilities,
                              including disposal of works effluent, storm water and site
                              drainage, and sewerage disposal should be available at
                              the site.
                      1.2.8   All site areas which are not sealed should be maintained
                              in a clean and tidy condition. Stored material on the site
                              should be kept in an orderly manner 300mm above the
                              ground in a well-drained positions or on pallets.

                      1.2.9   The exterior of the premises should be kept in good repair.

                1.3   Expansion
                      In planning the premises, careful consideration should be given to
                      the plan to allow space for future expansion.

                1.4   Soil Types
                      Care should be taken during site selection to avoid undesirable soil
                      types. Soil types subject to large expansion and contraction can
                      adversely affect construction costs or can cause serious damage to
                      buildings. Heavy soils subject to water lagging can create drainage
                      problems and allows pools of stagnant water to form.

                1.5   Water
                      1.5.1   An adequate supply of potable water must be available.
                      1.5.2   Depending on the source of supply, it may be necessary to
                              install an in-plant chlorination system or other treatment
                              systems to ensure potability of water at all times.